Hosted Teamwork Projects/Libraries

The Projects and Libraries panels are available for each selected BIMcloud Server or folder, on the Servers page of BIMcloud Manager.

They list all projects/libraries hosted by the current Server, even if they are not used by the Manager.

https://helpcenter.graphisoft.com/wp-content/uploads/bimcloud/30_bimcloudmanager/HostedProjects300090.png 

https://helpcenter.graphisoft.com/wp-content/uploads/bimcloud/30_bimcloudmanager/HostedLibraries00091.png 

Hosted Teamwork Projects/Hosted Libraries

Name: Name and path of the project/library. If the data is unused, then it displays the last known name and path of the data

Version: Version of the ARCHICAD project

Status: OK / Unused. A Status of Unused means that the Manager does not have any project/library which uses this data.

Last activity: Last time the data was accessed

Last backup 

Active users: Number of currently joined users in a project

Available commands for selected Project/Library

https://helpcenter.graphisoft.com/wp-content/uploads/bimcloud/30_bimcloudmanager/HostedFunctions.png 

Delete: Deletes the project/library

Load as new project/library: Only available for Unused projects/libraries. Creates a new project/library on the Manager from the hosted data.

Link to existing project/library: Only available for Unused projects/libraries. Links the data to a Missing project/library.

Missing or Unused projects/libraries

If the BIMcloud Manager refers to a project/library on a Server, but the project/library is no longer there, then it is listed in the Missing projects or Missing libraries section.

The BIMcloud Manager and the BIMcloud Server are separate programs. A project/library that is listed in the Navigator of the BIMcloud Manager must have a linked project or library data available on the Server as well. The reverse is also true: data hosted on the Server must be linked to a project/library entity on the Manager.

Sometimes the two components will become out of sync (e.g. one of the components was restored from a snapshot).

Depending on which component was rolled back, two kind of errors are possible:

Missing project/library: A project/library exists on the BIMcloud Manager (it is visible in the Project Navigator), but the data it refers to on the host Server is missing

Unused project/library: project/library data exists on the Server, but the BIMcloud Manager does not know about it and does not have a matching entry in the project/library Navigator

https://helpcenter.graphisoft.com/wp-content/uploads/bimcloud/30_bimcloudmanager/MissingProjects.png 

Available functions:

Delete: Removes the project from the BIMcloud Manager

Link to hosted project: The project/library can be re-linked to an Unused project/library hosted on the current or any other Server

  • Was this Helpful ?
  • YesNo
Relevant topics
Libraries in Teamwork
A Teamwork Project uses two types of libraries: the Embedded Library plus the BIMcloud Libraries. Just like in any ARCHICAD project, these ...