To view a Schedule that shows data only for selected Floor Plan items:
1.Select the desired elements (on the Floor Plan only). Use Find and Select if needed.
See also Find and Select Elements.
2.Select the desired Schedule in the Navigator Project Map or View Map.
3.Right-click the schedule name and choose “List Floor Plan Selection Only” to view schedule data for the selected items only.
This is a quick way to filter elements for editing as a group, by taking advantage of the Interactive Schedule capabilities. You cannot save a view out of the displayed data.
Relevant topics
Select Schedule Items on Floor Plan/3D
For any selected item in the Schedule Window, click the Select on Floor Plan icon to view it in the Floor Plan window.
The icon to ...
Floor Plan/Reflected Ceiling Plan Display (Stair Settings)
Each Stair has two groups of settings, defining display preferences for the Stair Symbol (and its components) on Floor Plan and on Reflected ...
Editing and Updating Schedule Items
To work on an item of the Interactive Element Schedule, click its column (or row). You will see that some of the cells of this column become ...